Process/         Activity Stage

Measurable Parameters Critical to Quality

Ref.Doc./Record

Parameter

Acceptance Criterion

 

1.

 

 

 

2.

 

 

 

 

 

 

 

3.

 

 

4.

 

 

 

6.

 

 

7.

 

 

 

 

8.

 

 

 

9.

 

 

10.

 

 

12.

 

 

13. & 14.

 

 

 

 

Location

Type of crop and its specifications

 

Quantity

Past Performance

 

 

Identification of squad members

 

Coverage and time

 

Parameters covered under activities (1) & (2)

 

Completeness and correctness

 

Availability

 

Time

 

 

Completeness of the information

 

 

Time

 

 

Completeness and legibility

 

Completeness

 

 

Time

Completeness

 

 

Time

 

Relevance

 

 

 

Procurement centres are identified for each type of  crop i.e.Rabi / Kharif along with GOI specification

 

The planning is based on the quantity being procured.

The Past Performance of the centre is also taken care of during planning.

 

Squad Team of the minimum 2 AMs having relevant field experience.

 

The time to be taken along with the coverage of procurement centre are also identified.

 

-do-

 

 

 

The proposal should be complete and correct in all respect.

 

Squad members should be available

 

Squad members should be intimated about the inspection at least one week advance.

 

Location of the procurement centres, period of inspection, inspection formats, foodgrains specifications shall be provided to the squad.

 

Within 15 days

 

 

All the formats shall be duly filled.  The format filled shall legible.

 

All the non-compliances shall be covered in the observations.

 

Within a week

All the observations shall be checked for the completeness before despatch.

 

ATR shall be received from procuring regions within 15 days except in case of any vigilance action.

The action taken shall be relevant to the observations.

 

 

Squad inspection file

 

 

 

Squad inspection file

 

 

 

 

 

 

 

Squad inspection file

 

 

Squad inspection file

 

 

 

Squad inspection file

 

 

Squad inspection file

 

 

 

 

Squad inspection report

 

 

Squad inspection report

 

Squad inspection report Format..

 

Squad inspection report

 

Squad inspection report

 

 

ATR

 

 

 

 

FCI

 Quality Plan

Doc.No. :QC/QP/01

Title : Monthly Technical Review

Page 1 of 3

Issue No.:01

Page Rev.No.00

Approved by :

 

Effective Date:

 

 

 

Process/         Activity Stage

Measurable Parameters Critical to Quality

Ref.Doc./Record

Parameter

Acceptance Criterion