Engineering. Division

  FCI  Quality System  Quality Plan Doc.No. :  
 

    Issue No.
  Title : Processing of proposals for construction of godowns/new godowns Page 1of
    Page Rev.No.
Approved by :   Effective Date:
             
Process/         Activity Stage Measurable Parameters (critical to Quality) Data to be kept Doc/Ref
Parameter Acceptance Criterion Method of check Doc/Ref.  
2. -capacity Based on the proposal submitted by FCI to Ministry for Monitoring
enhancement Storage capacity enhancement and construction Plan
cordination meeting is held for budget allocation and for
finalisation of list of approved centres.
3 -Capacity to be The communication should include - Total capacity to be Monitoring - Guidline Circular
developed built up centre wise and for preparation of preliminary to Zone Vide No._
estimate as per standard guidelines and drawings. Dt.__. - Ref.
-Time The communication to Zone be sent within a week of receipt Drg.No.__ Dt.__
of approval.
4 - Correctness of - Preliminary estimates are checked with respect to Calculation
estimate   standard guidelines and drawings for its correctness.
- Provision of -   Accessment of provision for ancillariessuch as office
Ancillaries and   block,switch rooms, tiffin rooms, security, roads and
site devlpnt.   developmentof site is made.
- Site condition - Site particulars shall be filled in site particulars proforma for
  assessing features of lands and any development.
- Cost index -  Cost index has been worked out on the basis of market
  rate and labour cost.
5 - Technical & - All provisions to be made keeping in view of site conditions
Financial   (i.e. level of surround,development of site, special treatment
  needed if any, siding feasibility)
- Checking of rates adopted and cost index.
7 Scrutiny & - Before submitting to the Competent Authority the proposal
recommendation   shall checked with reference to technical & financial
  'suitibility of estimate.
9 Approval Communication of approval of the Competent Authority for Monitoring
accord of AA &ES for further action for inviting tender after
following codal formalities at their end.
10. Value If the tender offer value is within one crore then it is finalised Monitoring DOP item No.28
at Zonal level.  If the tender offer is more than one crore then
itis submitted to Headquarters for its acceptance.
13. Based on the scrutiny of offer and Zonal Office Monitoring
recommendation offer is evaluated for its
approval/negotiation/ rejection.
11/16. - Correctness of The contract value and terms &conditions are checked with
value reference to the approval communicated.
- Scope and Scope & completion schedule of work is noted for purpose of
completion monitoring.
schedule of
work
17. - Physical & The progress is monitored through Monthly Progress Report
Financial received from zone on the Standard Proforma indicating
Physical & Financial Progress.
- Review Progress is reviewed quarterly during the meeting at PID
meeting Office.

 

FCI  Quality System  Quality Plan Doc.No. :  

 

 
  (ISO : 9001:2000 Clause 7.5) Issue No.  
    Title : Processing of proposals for construction of Regional/District  Page 1of
Prepared by :           Office Building.     Page Rev.No.
Approved by : Issued by : Effective Date:  
               
Process/         Activity Stage Measurable Parameters (critical to Quality) Responsibility Data to be kept 
Parameter Acceptance Criterion Method of check   Doc/Ref.  
1   I) Details The proposal should include thefollowing:- Monitoring      
    - Requirement on the basis ofsanctioned strength of        
    staff.        
    - Preliminary estimate        
    a) Requirement of covered area on the basis of        
    sanctioned strength.        
    b) Requirement of covered area for future expansion.        
             
  ii) Justification Justification and recommendations ofZonal Manager        
    - Requirement of building        
    - Feasibility        
2b. Scrutiny of - Covered area as per BPE norms Calculation   BPE/ FCI guidelines  
  Pre-estimate - Total cost on the basis of plinth area        
             
4   Submission of After scrutiny of the above proposalwith the        
  the proposal to recommendation of ED(Engg.)and ED(P) the proposal        
  the B.O.D for is put up toB.O.D by ED(P).        
  approval          
             
5   Communication Conveying the approval of BOD to the concerned        
    Zone/PID.        
             
7 & 8. Approval of a) If the estimated value is less than Rs. One crore the      
  estimate & NIT tender will beaccepted and awarded by the Zones and        
    copy of the award will be receivedby Headquarters.        
    b) If the estimated value is more than Rs. One crore        
    then the detailed estimate draft NIT will be sent to        
    Headquarters for approval alongwith thetechnical        
    sanction by Manager(Engg.)of the Zone.        
             
9     Receipt of the processed tender withrecommendation        
    of the Zonal Managerfor acceptance.        
             
10   Scrutiny of I) Duration from approved technical        
  tenders sanction/NIT        
    ii) Market rate verified by DM(Engg.)     DSR  
    iii) Credential verification of L 1        
    iv) Scrutiny of justification analysisdone by        
    Region/Zone        
    v) Checking of draft NIT        
    vi) Conditions of contract.        
             
14   Monitoring On receipt of the progress report in theprescribed        
    proforma on the progress ofconstruction will be        
    monitored forphysical and financial progress.        
             
15   Corrective Issue of guidelines for correctivemeasures, including        
  measure technical examination and technical audit.        

 

  FCI  Quality System  Quality Plan Doc.No. :    
 
  (ISO : 9001:2000 Clause 7.5) Issue No.    
    Title : Addition, Alteration & Maintenance of HQ Building &   Page 1of  
Prepared by :           Staff quarters.     Page Rev.No.  
Approved by : Issued by : Effective Date:
                 
Process/         Activity Stage Measurable Parameters (critical to Quality) Responsibility Data to be kept   
Parameter Acceptance Criterion Method of check   Doc./Ref.    
1   I) Preparation  As details of works to be executed estimate should          
  of detailed be prepared on thebasis of schedule of rate or          
  estimate analysis ofitems not covered under schedule.          
               
    - Anticipated present market value is added to          
    estimate.          
  ii) Time - within fortnight          
               
3   i) Technical Technical sanction of proposal should          
  sanction include :-          
    I) Schedule of quantity          
    ii) Abstract of value of work on the          
    basis of current schedule of rates          
    iii) Market rate analysis of items not          
    covered under the schedule.          
    iv) Present market rate of material &          
    labour.          
    v) Analysis of total cost on the present day value.          
               
  ii) NIT NIT to include:-          
    I) Specification of items          
    ii) Terms & Conditions of contract          
    iii) Schedule of abstract of works as per approved          
    technical sanction.          
    iv) Likely period of completion          
  iii) Value - Upto Rs.4 lacs the approval can be given by     DOP    
    DM(Engg.)          
    - Above Rs.4 lacs & upto Rs.25 lacs the approval          
    can be given by JM(Engg.)          
    - Above Rs.25 lacs the approval can be given by          
    M(Engg.)          
               
4. Call of tender Value Publication as per guidelines for different value of     FCI guidelines    
    tenders          
               
5. Processing   As per standard guidelines          
               
7. Monitoring   The progress of work is monitored as per work