Engineering. Division
| FCI | Quality System Quality Plan | Doc.No. : |
|
||||||
|
(ISO : 9001:2000 Clause 7.5) | Issue No. | |||||||
| Title : Processing of proposals for construction of Regional/District | Page 1of | ||||||||
| Prepared by : | Office Building. | Page Rev.No. | |||||||
| Approved by : | Issued by : | Effective Date: | |||||||
| Process/ Activity Stage | Measurable Parameters (critical to Quality) | Responsibility | Data to be kept | ||||||
| Parameter | Acceptance Criterion | Method of check | Doc/Ref. | ||||||
| 1 | I) Details | The proposal should include thefollowing:- | Monitoring | ||||||
| - Requirement on the basis ofsanctioned strength of | |||||||||
| staff. | |||||||||
| - Preliminary estimate | |||||||||
| a) Requirement of covered area on the basis of | |||||||||
| sanctioned strength. | |||||||||
| b) Requirement of covered area for future expansion. | |||||||||
| ii) Justification | Justification and recommendations ofZonal Manager | ||||||||
| - Requirement of building | |||||||||
| - Feasibility | |||||||||
| 2b. | Scrutiny of | - Covered area as per BPE norms | Calculation | BPE/ FCI guidelines | |||||
| Pre-estimate | - Total cost on the basis of plinth area | ||||||||
| 4 | Submission of | After scrutiny of the above proposalwith the | |||||||
| the proposal to | recommendation of ED(Engg.)and ED(P) the proposal | ||||||||
| the B.O.D for | is put up toB.O.D by ED(P). | ||||||||
| approval | |||||||||
| 5 | Communication | Conveying the approval of BOD to the concerned | |||||||
| Zone/PID. | |||||||||
| 7 & 8. | Approval of | a) If the estimated value is less than Rs. One crore the | |||||||
| estimate & NIT | tender will beaccepted and awarded by the Zones and | ||||||||
| copy of the award will be receivedby Headquarters. | |||||||||
| b) If the estimated value is more than Rs. One crore | |||||||||
| then the detailed estimate draft NIT will be sent to | |||||||||
| Headquarters for approval alongwith thetechnical | |||||||||
| sanction by Manager(Engg.)of the Zone. | |||||||||
| 9 | Receipt of the processed tender withrecommendation | ||||||||
| of the Zonal Managerfor acceptance. | |||||||||
| 10 | Scrutiny of | I) Duration from approved technical | |||||||
| tenders | sanction/NIT | ||||||||
| ii) Market rate verified by DM(Engg.) | DSR | ||||||||
| iii) Credential verification of L 1 | |||||||||
| iv) Scrutiny of justification analysisdone by | |||||||||
| Region/Zone | |||||||||
| v) Checking of draft NIT | |||||||||
| vi) Conditions of contract. | |||||||||
| 14 | Monitoring | On receipt of the progress report in theprescribed | |||||||
| proforma on the progress ofconstruction will be | |||||||||
| monitored forphysical and financial progress. | |||||||||
| 15 | Corrective | Issue of guidelines for correctivemeasures, including | |||||||
| measure | technical examination and technical audit. | ||||||||
| FCI | Quality System Quality Plan | Doc.No. : | |||||||
|
(ISO : 9001:2000 Clause 7.5) | Issue No. | |||||||
| Title : Addition, Alteration & Maintenance of HQ Building & | Page 1of | ||||||||
| Prepared by : | Staff quarters. | Page Rev.No. | |||||||
| Approved by : | Issued by : | Effective Date: | |||||||
| Process/ Activity Stage | Measurable Parameters (critical to Quality) | Responsibility | Data to be kept | ||||||
| Parameter | Acceptance Criterion | Method of check | Doc./Ref. | ||||||
| 1 | I) Preparation | As details of works to be executed estimate should | |||||||
| of detailed | be prepared on thebasis of schedule of rate or | ||||||||
| estimate | analysis ofitems not covered under schedule. | ||||||||
| - Anticipated present market value is added to | |||||||||
| estimate. | |||||||||
| ii) Time | - within fortnight | ||||||||
| 3 | i) Technical | Technical sanction of proposal should | |||||||
| sanction | include :- | ||||||||
| I) Schedule of quantity | |||||||||
| ii) Abstract of value of work on the | |||||||||
| basis of current schedule of rates | |||||||||
| iii) Market rate analysis of items not | |||||||||
| covered under the schedule. | |||||||||
| iv) Present market rate of material & | |||||||||
| labour. | |||||||||
| v) Analysis of total cost on the present day value. | |||||||||
| ii) NIT | NIT to include:- | ||||||||
| I) Specification of items | |||||||||
| ii) Terms & Conditions of contract | |||||||||
| iii) Schedule of abstract of works as per approved | |||||||||
| technical sanction. | |||||||||
| iv) Likely period of completion | |||||||||
| iii) Value | - Upto Rs.4 lacs the approval can be given by | DOP | |||||||
| DM(Engg.) | |||||||||
| - Above Rs.4 lacs & upto Rs.25 lacs the approval | |||||||||
| can be given by JM(Engg.) | |||||||||
| - Above Rs.25 lacs the approval can be given by | |||||||||
| M(Engg.) | |||||||||
| 4. Call of tender | Value | Publication as per guidelines for different value of | FCI guidelines | ||||||
| tenders | |||||||||
| 5. Processing | As per standard guidelines | ||||||||
| 7. Monitoring | The progress of work is monitored as per work | ||||||||